Customer References
Customer Comments
Reducing Truck Body Deterioration
Costs
in the Mining of Abrasive Material
| |
W. R. Yates
Manager, Mining
Rio Tinto Argyle Diamonds
Western Australia
Prepared for MinExpo International ‘96
Transportation Session September 12, 1996 |
Neither the author, nor Argyle Diamonds,
accepts responsibility for any adverse event
or occurrence which may arise from the use of any information presented in this
paper. |
| NOTES: |
1. This paper was originally presented in 1996 at MinExpo
International.
2. The contents and data included in this paper represent
the experience of
one operator using Duratray SDBs in extreme conditions, with
exceptionally abrasive materials.
3. It has been reformatted from its original form to enhance
readability. |
The Argyle Diamond Mine is an open pit operation
located in the North East
Kimberley region of Western Australia. It is operated on a 2-weeks-on
and 2-
weeks-off, fly-in/fly-out basis, and currently has an overall
mining rate of 48M
metric tons per year (53M US tons).
This remote area is characterized
by consistently high temperatures and a short
but intense wet season that yields about 1 meter (39”)
of rainfall annually.
A large percentage of the material mined is a
hard, blocky, and highly abrasive
quartzite rock with a UCS of 250 MPA.
The mine commenced in December,
1985, mining at a scheduled rate of 12M
metric tons per year, using 11 x CAT 777B haul trucks, loaded
by CAT 992C
front-end loaders. The 70-ton haul trucks were fitted with Heavy
Duty steel
bodies, lined with 12mm (1/2”) Bisalloy 360 wear plate
kits (Rockwell 39-43R)
and Dua plate hard-faced composite in the “dovetail” section.
The blocky material caused some deformation to
occur on the body liners, which
exacerbated the high wear rates induced by the high-silica rock.
The first of
these bodies failed at 1,000 hours of use and the remainder within
1,250 hours.
These bodies were refurbished
on-site using a contractor, and were fitted with
25mm (1”) Bisalloy 360 wear kits and again Dua plate in
the “dovetail” section.
The bodies fitted with the 25mm wear kits were able to achieve
a life of 2,500 to
3,000 hours between rebuilds. On the haul distances at that time,
this
represented 14,000-17,000 loads between rebuilds.
it was necessary to hold two spare bodies on-site
and a contract work force of
six (6) was permanently allocated to body repair. The average
cost of rebuild at
the time was AUS$35,000, and this was increasing with successive
rebuilds.
In 1988, a SKEGA Suspended Dump Body (SDB) was
imported and trialed on one
of the CAT 777B haul trucks for a period of approximately 6,000
hours. The haul
truck fitted with the SDB was 7 metric tons lighter than the
average Tare weight
of the remaining fleet equipped with steel bodies. Two weight
studies indicated
that the SDB truck had an average payload of 6.78 metric tons
heavier than the
fleet average-an almost 10% payload increase. The truck
was noticeably faster
when empty than the other trucks, and also ran below the fleet
average in fuel
consumption. it is acknowledged that fuel consumption at the
time was variable
and there was no study undertaken to attempt to scientifically
evaluate the
difference.
Carry-back, which was occurring in the front corners
of the steel tray (approx. 3-
4 tons per load), was never observed to occur with the SDB unit.
two problems were encountered with the SKEGA SDB
unit. The first was that
during tipping, the front of the truck became light, particularly
when dumping on
a down slope. This was attributed to the extended tail fitted
to this unit and the
observation that the load did not slide out of the body the same
way as it did
from the steel-lined bodies.
The second problem was that substantial cracking
started to occur on the main
steel frame. All of the cracking was associated with the welded
joints. Full scale
testing by consultant metallurgists found major defects in many
welds, with low
penetration and voids occurring.
Repairs were undertaken and the frame was fully
instrumented when it was
recommisioned to establish the actual levels of stress being
experienced during
use. This testing indicated that the stress being experienced
was within the
design specification and that if properly welded, major problems
should not
occur.
Extrapolation of of the wear rates occurring on
the suspended rubber body liner
projected a life of around 8,000 hours, or 46,000 loads.
The trial of the SDB was considered promising
enough that when a decision was
made to upgrade the haul fleet in 1990 to CAT 785B trucks, they
were all
supplied with SDBs. In these trucks, the steel frames were manufactured
in
Australia by Forward Engineering who had extensive experience
in the fabrication of dump bodies for the mining industry.
No spare dump bodies were
ordered for the CAT 785B trucks and only spare components were
held.
During the life of these trucks a number of modifications
were made to
theoriginal concept aimed at maximizing the life of the rubber
components.
A separate under-body support was developed for
the tail area that positively
located the suspension ropes and removed the need for grooving
the tail area of
the main mat, thereby increasing the available wear material
and strength in this
area.
Lower wear rates were achieved later by inverting
the main mat so that the
outside of the mat, as it was manufactured on the cylindrical
mandrel, became
the inside of the dump body. This change achieved some degree
of compression
on the inner mat face.
The CAT 785B fleet was operated for some 18,000
hours and the SDB achieved
the following:
• Average
mat life 10,000 hours (56,000 loads)
• NO major frame cracking
• Normal tipping performance
• Total elimination of carry-back
The CAT 785B trucks were sold in mid-1993 and
replaced with CAT 789 units at
the Argyle site which are fitted with Duratray SDBs.
The majority of the CAT 785B units have continued
to work in Australia and have
exceeded 40,000 hours, some reportedly still fitted with the
rubber mats that
were in place when they left Argyle. Although the operating conditions
are not as
harsh as those at Argyle, it stands testimony to the frame design
and
construction of the SDB.
The first CAT 789 trucks,
again fitted with SDBs, arrived in 1993 and at the time
of writing there are 13 trucks in the fleet. The loading of these
trucks is
predominantly undertaken by O&K RH2000 hydraulic excavators
in face shovel
configuration with bucket sizes ranging between 21m3 and 23m3.
Back-up
loading capacity is provided by a CAT 994 front-end loader.
The CAT 789 haul trucks are fitted with the Cat
TPMS (payload monitoring
system) linked to a modular dispatch system, allowing direct
monitoring of truck
loading. Some trucks have now reached 18,000 of operation and
have achieved
the following results:
• Average
payload 177.2 metric tons (195 US tons)
• Average rubber mat life 14,000 hours (68,000 loads)
• Normal stability during tipping
• No carry-back
• No frame cracking
The only problem
encountered in early use was that occasionally the body could
not be hoisted. This occurred mainly when the truck was in fact
under-loaded,
but the payload placed forward in the body. The situation was
rectified when the
body was extended about 1m at the rear allowing the load to be
located a little
further rearward. AN electronically controlled two-stage pressure
relief valve was
also fitted to the truck hydraulic system. The valving allowed
the use of higher
pressure for initial hoist and normal pressure to be used for
the full hoist cycle.
The manufacturer has recently modified the under-body
support for the floor
mat, which is expected to further increase mat life.
Cost of Ownership Comparison
Cost comparisons have been undertaken between the
HD steel bodies and the
Suspended Dump Bodies at various stages in their use at the Argyle
site. These
commenced with analysis and comparison directly of the bodies
fitted to the 70T
CAT 777B trucks, and subsequently by extrapolation of that data
and supplier
costing at each fleet change.
The Duratray SDBs have enjoyed a substantial cost
advantage at each analysis.
For the cost comparisons, it has been assumed
that the wear rates experienced
in the first three (3) years of the operation of the steel bodies
would have
remained constant on a number of loads carried basis. the following
procedure
has been used to estimate the costs of HD steel bodies and SDBs
fitted to the
current fleet of 13 x CAT 789 haul trucks in use at the Argyle
mine.
| • |
Capital costs have been established
from current supplier quotes. |
| • |
The capital cost of the HD steel bodies
is calculated to include the cost of two spare bodies (ie,
the capital cost of 15 HD steel bodies divided by 13 trucks
is the per-body capital cost applied.) |
| • |
The repair frequency of the steel
is based on the maximum number of loads that were previously
achieved and the hours adjusted to the current haul profile. |
| • |
The repair costs used for the HD steel
body are from supplier quotes, while those for the SDBs are
as currently invoiced. |
| • |
The costs have been estimated over
a four (4) year period of 24,000 operating hours, as this
is the frame over which Argyle has current experience. |
The results are shown in Table 1 below. Costs
are shown in Australian dollars.
| |
HD Steel Body |
Duratray SDB |
|
| Annual truck operating hours |
6,000 |
6,000 |
|
| Capital cost of tray (A$) |
260,000 |
350,000 |
|
| Capital cost of spare tray (A$) |
40,000 |
----- |
|
| Total Capital cost per truck (A$) |
300,000 |
350,000 |
|
| Operating hours to rebuild |
3,500 |
14,000 |
|
| Repair frequency per year |
1.71 |
.428 |
|
| Cost of repair (A$) |
85,750 |
29,960 |
|
| Cost of repair per year (A$) |
146,630 |
29,960 |
|
| 4-year period per truck (A$) |
886,530 |
469,840 |
(-47%) |
...On this basis, the Duratray SDBs achieved a
47% lower cost of ownership over
the 4-year period.
Life of Truck Comparison
The original steel trays fitted
to the CAT 777Bs were experiencing severe
cracking and deterioration of the main bodies after only 6 to
7 rebuilds (18,000-
20,000 hours) and rebuild costs were increasing. It was anticipated
that the HD
steel bodies would require replacement at a life of 24,000 hours.
The current
indicators are that the SDB frames will achieve a life of at
least 40,000 hours at
Argyle. On this basis:
| • |
At
40,000 hours per SDB, 13 SDBs would achieve 520,000 hours
before replacement. |
| • |
At
a projected rubber wear rate of 14,000 operating hours,
SDBs would require 37 rebuilds over the fleet life. |
| • |
At
24,000 hours per steel body, 15 bodies would achieve 360,000
hours before replacement. |
| • |
At
a projected steel body wear rate of 3,500 operating hours,
steel bodies would require 149 rebuilds over the fleet
life. |
| |
HD
Steel Body |
Duratray
SDB |
| Capital
Cost |
30 x
260,000 = A$ 7.80M |
13 x
350,000 = A$ 4.55M |
| Repair
Cost |
149 x
85,750 = A$ 12.78M |
37 x
70,000 = A$ 2.60M |
| Total Cost |
A$
20.58M |
A$
7.15M |
...An estimated savings of 64% in total dump body
cost.
There are a number of less direct benefits that have been observed
during the
last six years of operating a haul truck fleet fitted with Suspended
Dump Bodies
at the Argyle Mine.
| • |
A substantial
reduction in shock to the truck operator during loading |
| • |
A substantial
reduction in noise during loading, which may be significant
in poplulated areas |
| • |
A reduction
in the truck downtime associated with body repairs and a
major reduction in the labor requirement for dump body maintenance.
The replacement of the SDB components does not require specialist skills
or equipment. |
| • |
The elimination
of carry-back |
| • |
Reduced
spillage on pot-holed roads where the dump body flexes on
impact, reducing ejection of rock from the body |
| • |
Lower shock
during loading may reduce load transfer to the main frame
of the haul truck. This has not been measured at Argyle. |
Operating conditions with the mining and earthmoving industry
vary enormously.
This paper summarizes the experience at the Argyle Mine and the
particular
conditions found at that site. Other operations will have to
assess the particular
applicability of the SDB concept to the conditions encountered
at each location.
|